Opus Time Lapse: ArborBLU June 2015 Construction Update

More about this project
6/16/2015
Tags:

​Construction is in full swing at ArborBLU, a luxury student housing development in Ann Arbor, Mich.

Now that the superstructure is fully erected, the tower crane is being taken down this month. Windows are punched on levels three to 12 and glass has been installed through level 11. Elevators are being installed with completion and turnover for construction use in mid-July. Drywall and finish is complete on level four and underway on levels five to seven with painting, cabinetry and other finish work underway on levels four and five.

The building will welcome its first residents before the beginning of the fall semester.