Opus Time Lapse: The LAB January 2015 Construction Update

More about this project
1/22/2015
Tags:

Once completed, The LAB will be a transit-oriented, boutique office building in along Denver’s historic Platte Street.

Steel erection completed at the end of December. Throughout January, the team will have composite deck and slab-on-grade pours and roof installation complete. Masons will also start on the east and south elevations with exterior framing/sheathing 75% complete and mechanical, electrical and plumbing rough-in will begin. 

The building is scheduled for completion in June.