Paragon Business Park July 2015 Construction Update

7/22/2015
Tags:

‚ÄčOn schedule to complete in September despite a very rainy summer, work continues at Paragon Business Park in suburban Chicago.

With the building pad continuing to dry out, the fire sprinkler valve and pump and electrical conduit are being installed. Docks and the electrical/pump room slabs were poured with work continuing with masonry through the end of the month. Grading on the berm has progressed and some landscaping will be added as weather allows.

The interior painting is complete with the exterior painting 25% complete.