Paragon Business Park May 2015 Construction Update


​With rain pouring down on the site, the construction team has focused on managing water on the site. Both buildings are fully roofed and watertight and excess water is being pumped from the building pads to accelerate the drying process. Site utilities will be finished by early June with the water main connection as the last step.

Once completed, Paragon Business Park will include two spec industrial buildings that can accommodate single- or multi-tenant occupancy. Construction is slated for completion in late summer.